Lead times and delivery schedule

Current planning lead times by product line and what each stage takes.

Updated November 27, 2026

ItemPlanning lead timeNotes
Parts in stockFast deliveryCourier or LTL
Blast wheel rebuild or exchange1 to 2 weeksExchange units available
Control panel or HMI upgrade4 to 8 weeksIncludes design, build, program and install
Standard deflash model10 to 14 weeksDEF-DB, DEF-TMB, DEF-WMB, DEF-INDEX
Spinner hanger or table blast12 to 18 weeksCustom hooks and fixtures add 2 weeks
Air blast booth12 to 16 weeksDepends on recovery floor option
Plate and structural line16 to 24 weeksConveyors and ducting included

Planning values, updated November 2026. Lead time starts at drawing approval. Read the delivery guide for what happens in each stage.