Delivery and lead times

What happens between the PO and the first part off the line, and how long each step takes.

By Surface Technologies engineering · Updated November 27, 2026 · 2 min read

Typical lead times

Lead time depends on the machine type, the options and how quickly drawings are approved. Standard models with published specifications are the quickest. Engineered wheel blast lines take longest, because conveyors, ducting and controls are built around the part. Current planning figures are kept on the lead times page so they can be updated in one place.

The sequence

Order; engineering approval drawings; fabrication; assembly and testing before delivery; crating and shipping; installation and commissioning; operator and maintenance training.

Shipping

Machines ship from Ontario. Smaller machines travel as one piece; long lines ship in sections. Rigging and craning at your end are planned with you before the truck is booked.

Installation

A compact machine can be set, levelled, connected and run quickly. A wheel blast line takes longer, depending on conveyors, ducting and controls.

What slows things down

Late drawing approval, utilities not ready on site, and custom tooling decided after the order. Lock those three early and most projects stay on schedule.

What you can do to shorten it

Return approval drawings quickly, confirm utilities and floor layout early, and decide on options before fabrication starts. Late changes to work-opening size, voltage or automation are the usual cause of slipped dates.

Acceptance before shipping

A machine that is assembled and run before it leaves the builder arrives with fewer surprises. If your parts are available, running them at this stage is the best check of cycle time and finish. Agree in advance what will be demonstrated and who will attend.

Preparing the site in parallel

While the machine is being built, the foundation or pit, power feed, compressed air drop, ducting route and any conveyors that feed the cell can be completed. The pre-installation checklist on this site lists the items in the order they are usually needed.

Commissioning and training

Commissioning covers levelling, connecting utilities, loading abrasive, setting the blast pattern and proving the cycle on production parts. Operator and maintenance training at the machine, on your own parts, is worth more than any manual.

Tell us about the part

Send a drawing, a photo or the part details. We recommend the machine that fits and quote it.