Delivery and lead times
What happens between the PO and the first part off the line, and how long each step takes.
Typical lead times
Lead time depends on the machine type, the options and how quickly drawings are approved. Standard models with published specifications are the quickest. Engineered wheel blast lines take longest, because conveyors, ducting and controls are built around the part. Current planning figures are kept on the lead times page so they can be updated in one place.
The sequence
Order; engineering approval drawings; fabrication; assembly and testing before delivery; crating and shipping; installation and commissioning; operator and maintenance training.
Shipping
Machines ship from Ontario. Smaller machines travel as one piece; long lines ship in sections. Rigging and craning at your end are planned with you before the truck is booked.
Installation
A compact machine can be set, levelled, connected and run quickly. A wheel blast line takes longer, depending on conveyors, ducting and controls.
What slows things down
Late drawing approval, utilities not ready on site, and custom tooling decided after the order. Lock those three early and most projects stay on schedule.
What you can do to shorten it
Return approval drawings quickly, confirm utilities and floor layout early, and decide on options before fabrication starts. Late changes to work-opening size, voltage or automation are the usual cause of slipped dates.
Acceptance before shipping
A machine that is assembled and run before it leaves the builder arrives with fewer surprises. If your parts are available, running them at this stage is the best check of cycle time and finish. Agree in advance what will be demonstrated and who will attend.
Preparing the site in parallel
While the machine is being built, the foundation or pit, power feed, compressed air drop, ducting route and any conveyors that feed the cell can be completed. The pre-installation checklist on this site lists the items in the order they are usually needed.
Commissioning and training
Commissioning covers levelling, connecting utilities, loading abrasive, setting the blast pattern and proving the cycle on production parts. Operator and maintenance training at the machine, on your own parts, is worth more than any manual.
Related
Shot blast machine maintenance schedule
Daily, weekly, monthly and annual tasks that keep wheels throwing and seals sealing.
Total cost of ownership
Media, power, wear parts, labour and downtime: what a blast machine really costs per year.
Shot blasting vs sandblasting
Wheel versus air, steel versus mineral media, and which one your part actually needs.
ApplicationsBrowse by application
Descaling, coating preparation, casting cleaning, peening, deburring and deflashing.