Pre-installation checklist
Everything to have ready on site before the truck arrives.
Site
- Level, reinforced slab poured and cured (6 in minimum)
- Pit or trench complete if the GA drawing shows one
- Clear path from the dock with door widths and ceiling heights checked against the GA
- Rigger or forklift arranged for the delivery day
Electrical
- Disconnect installed at the machine location, sized per the utilities list
- Conduit run to the panel location
- Certified electrician booked for the connection
- Network drop at the panel if remote support is in scope
Air and ventilation
- Compressed air drop with regulator and dryer at the machine
- Dust collector set, ducted and wired
- Exhaust routed to outdoors or make-up air planned
Process
- Media on site in the specified size and quantity
- Sample parts and fixtures available for commissioning
- Operators and maintenance staff scheduled for training
- Finish spec and acceptance criteria agreed in writing