Pre-installation checklist

Everything to have ready on site before the truck arrives.

Updated November 27, 2026

Site

  • Level, reinforced slab poured and cured (6 in minimum)
  • Pit or trench complete if the GA drawing shows one
  • Clear path from the dock with door widths and ceiling heights checked against the GA
  • Rigger or forklift arranged for the delivery day

Electrical

  • Disconnect installed at the machine location, sized per the utilities list
  • Conduit run to the panel location
  • Certified electrician booked for the connection
  • Network drop at the panel if remote support is in scope

Air and ventilation

  • Compressed air drop with regulator and dryer at the machine
  • Dust collector set, ducted and wired
  • Exhaust routed to outdoors or make-up air planned

Process

  • Media on site in the specified size and quantity
  • Sample parts and fixtures available for commissioning
  • Operators and maintenance staff scheduled for training
  • Finish spec and acceptance criteria agreed in writing